Visit this page often for updates. Images and videos can be seen below. Restoration of this vintage yacht is progressing along. The rain has slowed the progress just a bit, however the crew is pressing along as best as possible.
Many layers of paint and epoxy coatings removed:
December 23; Haul-out,
Early January to April - Remove damaged Planking
Early January - Start Removal Damaged Frames
Early January - Remove Diesel motor
Mid January - Start to Fabricate Replacment Frames
Late January/ April - Install Replacment Frames
April / May - Fabricate and install Replacement Planking
May - Motor Installation
May - Epoxy wood coat
May - Bottom Paint
June - Water Maker Installation
June - Nav Instruments instaled
June - New Inverter and Gel Cell Batteries.
June - Install masts and booms, rigging
Late June - Install interior
July/ August - Sail Testing & Commisioning Systems